Shipping and Covid

Electric Brewing Supply strives itself on fast turnaround of your order, however during these times of uncertainty and instability in both shipping and supply, we have been working hard to provide as prompt a service as we can.  It is important to note that during these pandemic times, the shipping carriers are overwhelmed themselves and are seeing volumes equal to or greater than what they would often see during the holiday rush.  For that reason, combined with the difficulties the pandemic has proven, for reliable labor, the carriers have dropped nearly all their service guarantees. 

What does this mean for you?

While we strive to ship within 1-2 business days of your order being received, no matter what the software states for an estimated delivery date, this is in fact an estimate.  The carriers will do their best to meet that target, but as trends are showing, they have had a difficult time doing so.  If something is critical, please think about having your order shipped UPS Next Day Air or 2nd Day air as they tend to be the most reliably delivered (albeit, the delivery may be late in the day).  Priority Mail has shown to be a best estimate and whether you select it or we use it for our flat rate per usual practice, we can't and they won't, guarantee your delivery.

Planning for the holiday

At the moment kits and builds are seeing significant delays across all supply chain channels, from our Chinese sources to our US made sources, everyone is backing up.  We have been working hard to mitigate this problem by way of alternative vendors and manufacturers, however we are beginning to see large cracks appearing in even our back ups.  The electrical industry as whole has been hit hard by demand created by construction but also from destruction caused by natural disasters such as hurricanes.

For the best estimate for a delivery time on product you are interested in, please reach out to us.  While most of the parts are listed as in stock, and very likely are, a few may be out of stock, but not reflected in the inventory correctly at this time. Our production process can often mix up numbers for a day or few.

Products currently see delays, or anticipated outages include:

  • Breakers
  • PIDs
  • Temperature probes
  • Temperature probe cables
  • Enclosures

 

Products we're seeing fewer troubles with

  • Outlets
  • Contactors
  • Inlets to a degree
  • Plugs
  • Wire and cable

UL listed products will vary considerably as some products are in stock, but delayed due to vendor moves or out of stock due to production shortages. 

Lead times of up to 6-8 weeks are proving to be more normal than the exception right now.  Please, if you have any questions, reach out to us.

Thank you

Ryan Gray
President and Owner
Electric Brewing Supply